NTPC Talcher - TPS 2X110MW:

The scope includes the engineering, supply, erection and commissioning of burner panel assemblies (wind boxes), oil station and firing system, SADC and BTC power cylinders, control valves, flame scanners, igniters and state of art furnace safeguard and supervising system (FSSS). The contract value was INR 19 Cr. for both units of 2X110MW. Each unit was erected & commissioned in 41 days of shutdown against targets shutdown period of 45 days. The trial run & PG test also completed within two months of unit synchronization in Dec'2011. During execution all safety measures were taken care and NGSL ( formerly NASL) got best contractor safety award from NTPC TALCHER.